Resource EvaluationProduce and complete a a Gantt Chart usin

Resource EvaluationProduce and complete a a Gantt Chart using MS Project software.Using the Table below enter the information into MS Project software. Assume that each resource has been assigned to the project activity on a full-time (8 hours /day or 40 hours per week) basisActivityDurationPredecessorsResource AssignedA. User Survey4NoneGail WilkinsB. Coding12ATom HodgesC. Debugging5BWilson PittsD. Design Interface6A,CSue RyanE. Develop Training5DReed TaylorInclude a title page and adhere to the Publication Manual of the American Psycholgical Association (APA), (6th ed., 2nd printing) when writing and submitting assignments and papers.